Ebe Scherkus
Analyst · Credit Suisse
Thanks, Sean, and good morning, everyone. Well, LaRonde, I would say had a reasonable quarter but not a great quarter. The milling capacity was restricted by 2 things, one a planned 5-day shutdown and then also we were having some issues with obtaining cyanide, and that appears to have been resolved. But in the meantime, the mine functioned well, while we were sort of choking back the mill. We did manage to stockpile additional ore on surface, and that will be processed by the end of the year. Recoveries essentially are according to plan. But the big story at LaRonde is it is a mine in transition. We are currently mining there our stopes. So as a result, we are getting some higher dilution. But the big story is LaRonde expansion will be ready by the fourth quarter of this year. Work has progressed very, very well. The load up facilities, the crushing plant, all of it will be ready by Q4. And we expect to be able to extract our first mining block, a higher grade mining block in October, November of this year. In the big picture from a CapEx side, this was one of our more complicated projects with an overall budget of $265 million. It will be coming in on time at approximately $15 million under budget. So they did very well. At Goldex. Goldex actually had a great performance from a material's handling point of view. It had record tonnage in May and June following modifications to the tailing spawn system. Our operations continue to be under control. Our cost per tonne is actually under budget, but our CapEx are over budget. And I would just like to talk a bit about the surface subsidence issue. About 4 months ago, we blasted on the Goldex Expansion Zone, and we re-hit a shear zone that lies above the eastern part of the Goldex Expansion Zone and that has been the source of water. We started getting an increase of water from another blast, a little over a year ago and that was a major blast, so we started getting some infiltration. Goldex is historically a dry mine. And so it's not equipped to handle a lot of water, unlike some of our other mines at Pinos Altos and even Kittila. So we started getting some water inflow and that inflow gradually increased over the year. So the impact of that water inflow, it lowered the water table and the overburden on top of the deposit and the overburden averages of anywhere from about 75 feet to 150 feet in thickness. So our program of mitigating this issue consists of grouting the shear zone to prevent the water from inflowing into the mine, reinjecting water to restore the water table and then also increase our pumping capacity in the event that we're not able to totally seal off the shear zone. So far, we have had -- it's still very early, but we have had some initial good results. Our pumping capacity has been increased significantly. So as a result, we have started to reinject our water table, water into the water table, and the early results are positive where subsidence, or the rate of subsidence, has declined. At no point or anywhere is the water table or the orebody in jeopardy. We have been pumping water and yet we have been able to establish record tonnage in May and in June. But with respect to the CapEx, we have taken a provision. We've only spent $6 million of that so far. But we have taken a provision to continue this program to make sure that we complete it from now to the end of the year. But, we will be doing more grouting, more injection and then also we will be pumping. So we'll keep you posted if there are any more changes. But so far, the initial results have been positive. With respect to exploration, the big news is the results on the D zone at depth. This is a zone that we knew about back in 1996. We only had a few drill holes in it. However, we decided not to follow up on it at that time. But with the completion of production and development on the Goldex Expansion Zone, we now started to drill it. And part of that program is a 300-meter ramp below the existing workings. And so far, what we have found are thicknesses equivalent to the Goldex Expansion Zone, grades equivalent to the Goldex Expansion Zone, and although the resource that we have calculated so far of about 75% of 1 million ounces of gold, we can see, with these new drilling results, we can see that resource grow significantly over the coming year. For Goldex, the D zone has the potential to significantly extend the life of the mine. It could even eventually even be a repetition of the Goldex Expansion Zone, at least from the information that we have so far. At Lapa, this once again, our nickname for Lapa, it's the little mine that could. It has had steady-state performance exceeding its tonne hoisted and tonnes milled underground development. It's targets have been exceeded despite increased rehab and the difficult ground conditions. It's costs per tonnes are below budget. It's unit development costs are below budget. So overall, a very excellent performance from the Lapa, and the crew has to be commended for their hard work. Exploration. We've started an exploration drive out to the East. We are developing an east zone and should be able to extend the Lapa mine life by an additional 6 months. While we are drilling parallel to the Cadillac shear zone and we intend to methodically and systematically follow up on some previous surface drilling results that were quite interesting. So we'll keep you posted on exploration results at Lapa as they become available. At Kittila. Kittila from a grade point of view had an excellent quarter. Actually, it met its budget. We did have a planned shutdown for the autoclave. That shutdown was planned in April. What we did not expect was another one due to an agitator failure and brick lining failure a little over a month later, and that resulted in a second shutdown. But as a result of these 2 shutdowns, what we have noticed that some of the components, the agitator shafts, the pumps, et cetera, were not robust enough so we have been systematically upgrading the quality and the strength of the various components, and so we expect these types of issues to decline. Overall, gold recovery was on plan, averaging almost 83%. Currently, we're seeing 85% to 86%. Since the last shutdown, we have had excellent performance averaging once again, steady state over 3,000 tonnes per day. The grades have been in the 4.8 to 5.4 gram per tonne range, so that bodes well. We have 300,000 tonnes stockpiled on surface. We're back in the Suurikuusikko pit after delaying work in it for over 2 months, and that was part of the reason why some of our costs were high. We had higher than normal stripping costs. We did go into the Rouravaara pit, and we did extract some ore from that pit. But that pit as a contingency, had a significantly higher stripping cost than Suuri, and that is reflected in our cost per tonne. Had we made capacity and not had the stripping issues, the Kittila costs would have been approximately EUR 72 per tonne. And now what we are focusing on in the second half of the year is the continued elimination of contract workforce as we are transitioning to self-mining. These are underground and surface contracts that have helped us out with waste stripping. They have also serviced the mine and installed all of the facilities. And typically in Finland, they also muck out all of the development material. So Agnico will be taking this function over totally in the second half of the year. But also having said that, some other performance indicators. Underground development performance was excellent and on plan. Underground ore production, we hit our target. It was on plan. So basically, I think we're setting ourselves up for some significant cost reductions and better results in the second half of the year. I think the big news at Kittila are the exploration results at depth on the Rimpi Zone way to the North. To put it in perspective, like everyone that visited the mine site over the past year, when you look at this new current intersection, it is located approximately almost 1.5 kilometers further north away from the mine and at a depth of 850 meters. And as we were saying yesterday, every now and again, an intersection comes along and we'll think about going forward, and the significance of it, and this has the potential of being one of those intersections. It intersected over 21 meters of true thickness of 7.1 grams per tonne. So one of the best holes ever on the Suurikuusikko trend. So in light of our current expansion study, up to 4,500 tonnes per day, which we expect to complete by the fourth quarter of this year. We also have to start looking at how are we going to access this new deeper expansion. What are we going to do? And one of the options is an exploration shaft, and we will be providing you with more updates as our thinking evolves on that. Pinos Altos. There's not much that you can say about it. It had a record quarterly gold production. It was our flagship operation this quarter, over 51,000 ounces of gold produced. Cash cost below $300 per ounce. The underground mine averaged 3,000 tonnes per day in June. It's on time, on plan, actually ahead of plan. The open pit, great performance on a cost per tonne basis. So over on all cylinders, on all metrics. Pinos Altos performed exceptionally well. Mascota, the ramp up was faster than what we had planned. It contributed over 9,000 ounces to the Pinos Altos account. All in all, a great quarter for Pinos Altos. We are focusing on the satellite deposits. As you know, we have the center deposit. We had Cubiro and we're still drilling on them. We are looking at the various ways of accessing them. So that will continue to be the focus going forward on Pinos Altos. Meadowbank. Well, we can also say it's a mine in transition from a mine that has caused us a lot of grief, especially over the last, I would say over the last year since the start-up. However, it did produce over 59,000 ounces of gold. But the cash cost of the denominator was just too low. So the costs were $910 per ounce. Now one of the main reasons for the low production was the dilution in the open pit. When you look at it on a cost per tonne basis, over the last quarter, our cost per tonne declined and this is currently around $81 per tonne in June. And with the current performance in July with the start-up of the secondary crushing plant, we expect to continue to see a downward trend. With respect to the dilution issue, so far, and it's still very early, we've only had a couple of blasts. And we have seen an approximate 50% reduction in our projection. For those of you who were up on the Analyst Tour in the end of June, we were getting displacements of the ore pile in the neighborhood of 10 to 13 meters. We are now seeing displacements in the neighborhood of 4 to 6 meters. And when you look at the performance of the plant itself in July, we are currently averaging 9,300 tons per day. Our recoveries are actually on plan, close to 94%. And the grades for the first time, our plan is 3.2 grams per tonne. And the current grade is 3.1 grams per tonne. So at least from the grade point of view being sent to the mill, we are very close to our plan. So if you do the math, Meadowbank so far as of the July 25 has produced close to 22,000 ounces. And when you put that into the context of the 59,000 ounces that we produced during an issue and trouble plagued quarter, we are well on our way to realize our objectives at the Meadowbank for the coming quarter. We've also been able to improve our operating staff. Positions have been filled. As we all know in the industry, labor and management, to be able to get that is challenging. But over the quarter, we have now virtually filled all of our positions. Our drills are currently performing well in the open pit. We are getting increased performance out of the open pit on the basis of tonnes hauled. However, CapEx has been an issue, and the biggest issue has been dyke construction and that has been the central dyke as part of our dewatering program on the Goose and Portage pits. When we did the detailed engineering, we were given a certain quantity of material. When we went into the pit and then started drilling and sounding for bedrock, we found in one location that rather than the expected 8 to 9 meters of overburden material, we found 17 meters of overburden. So as a result, the quantities required to build this dyke increased. So what we are doing now, we are looking at potentially modifying the design or seeing whether it could be modified to see whether we could reduce the quantities of material required for the dyke and reduce the CapEx. However, we have taken that provision and that is one of the reasons why there is an increase of CapEx at Meadowbank. Meliadine. Meliadine is another project in transition. We have just completed 100-man camp. We're just in the process of acquiring another 100-man module. And we're looking at increasing the number of drills on the property. We are also looking at increasing the underground development. We currently have a contractor on-site. We are in the process of rehabilitating the ramp and the underground workings that were initially put in by Comaplex. So they are on-site and that is going on schedule. But when you look at the overall challenge at Meliadine, we have to get the road permitted. That is what we are working on because we do want to accelerate the underground program. We are looking at a 4-year program that will enable us to be able to drill the Tiriganiaq zone at depth of below 350 meters. Now when you look at Slide 18, Page 18, the overall extensive property position. What this particular map just shows, these are grab samples that our geologists who went out into the field and systematically acquired by chipping away various outcrops that they saw. And so there are some very spectacular samples that we haven't even drill tested yet. And you could see Aklak 116 grams per tonne and Prairie 217 grams per tonne. So across the 80-kilometer strike length, or length of this property, what these samples show us is that there are numerous untested targets that we will be following over and above the Tiriganiaq and Wesmeg and Discovery zones that we currently have. When you look at Page 19, it shows what our thinking is with respect to the underground ramp expansion and proposal. Currently what we have rehabilitated is the ramp highlighted in black and that's where we will be taking an additional bulk sample later on this year to be able to validate the sample. But come spring, we would like to be able to continue with development and complete the area highlighted in red. And this would be a 4-year development program. Of course, the size of the program, the ramp and the location of the ramp, we would be able to use this underground infrastructure for production purposes going forward. So in summing things up, we have had a difficult quarter. There is no 2 ways about it. We have identified our issues and we are starting to see some of the results, positive results of these issues, especially at Meadowbank with the commissioning and start-up of the secondary crushing plant. We are seeing increased performance from the open pit and tonnage move. We are starting to see improving grades coming out of the pit. At Kittila, we're back in the Surry pit. We know we're going towards a high-grade cycle in the pit. We also know it's a more mature pit so the stripping ratio will decline significantly and that will reduce our mining costs. We also know that we are getting rid of a contract force on-site and going to self mining. And we also know that from our underground workings that the performance has been excellent from the development from the tonnes that have been coming out of Kittila. So there are a lot of positive signs. So with that, I'd like to turn you back over to Sean.