Thanks, Phil, and good morning. Starting on slide 7. At Skouries, construction activity in Q3 continued to ramp up with overall project progress at 34% and when incorporating all prior work, Skouries progress stands at 65% complete. Mobilization continued for major earthworks for construction haul roads needed to undertake all other major earthworks, and is progressing well with work on several fronts underway. During the quarter, the contractors for the earthworks and pilings for the primary crusher were mobilized and commenced work. General works continued to focus on site preparation, relocation of temporary facilities, recommissioning of the non-contact water reinjection well system, and the haulage of aggregates for construction purposes. The first phase of underground development continues to advance the west decline and lateral development for the test stopes to validate the underground assumptions prior to first production from the underground. Test stope work access will commence at the end of 2024 with expected completion by mid-2025. With year-to-date spending at Skouries at $101.3 million, we expect to ramp up our commitments during the fourth quarter and are comfortable achieving our updated guidance range of $160 million to $170 million. The spending is focused on completing detailed engineering and procurement. As of September 30th, detailed engineering is 56% complete and procurement is 73% complete. We continue to focus on completing key contracts with evaluations ongoing with a view to generating cost and productivity synergies during the process. We expect to complete this process and award the remaining key contracts by the end of 2023, which include the filter plant, including the earthworks, pilings, and foundation to support the filters. Open pit pre-stripping and construction of the ore stockpile, water management ponds, and the integrated extractive waste management facility dam embankment, structural concrete for the primary crusher and associated process facilities, and mechanical, piping, electrical, and instrumentation for the process plant. The project, both cost and schedule, remain on track for commissioning and first production in mid-2025 with commercial production expected at the end of 2025. Turning to slide 8, in the third quarter, we recorded zero lost time injuries. Lost time injury frequency rate for the first nine months of the year was 0.74, a 49% decrease from the same period in 2022. We continue to take proactive steps to improve workplace safety and to ensure a safe working environment for our employees and our contractors. On our operating results, we produced 121,030 ounces of gold in the third quarter with a cash operating cost of $698 per ounce sold, a solid quarter, which positions us to remain on track to meet our guidance. I’ll pass it over to Simon to review the third quarter performance and operations in Turkiye and Canada.