Thank you, David and good morning, everyone. As David mentioned, we've made strong progress on the execution of our growth projects since the beginning of the year and are extremely well positioned to continue to execute. At our Tucuma project, we concluded critical path of earthworks around our process plant infrastructure and poured first concrete in February on schedule. Overall, civil works are progressing well, and we expect completion of the primary crusher foundation later this month and the foundation for the Ball Mill to be completed in June. Electromechanical erection for both areas is scheduled to commence in July. I am pleased to report that equipment deliveries also commenced this quarter, most notably with the arrival of our Ball Mill on site. On the mining side, pre-stripping activities remain firmly ahead of schedule with approximately 20% of total prestrip volume completed as of quarter end. With all major outstanding contracts concluded during the period, capital expenditures under contract increased from 55% at year-end to approximately 85% at the end of March. With an additional 5% of capital expenditures currently in the final stages of negotiation, our overall visibility on total project spend is over 90%. Our capital estimate for project completion remains unchanged at approximately $305 million, which is within 4% of the feasibility study estimates. With a significant workforce mobilization currently underway at Tucuma, we have ramped up local labor chain programs in partnership with the National Service for industrial training, a well-known nonprofit organization focused on technical and vocational education in Brazil. In part due to the success of this program, approximately 60% of our 700-member workforce currently at the Tucuma project are from the surrounding communities. Switching gears to our Caraiba operations. We continue to advance surface infrastructure installations for the new external shaft, as can be seen in the photos included in yesterday afternoon's press release. Main activities underway on surface include final civil, erection of steel work for the headgear, Center Tower as well as installations of the stage and personal winders. In parallel, we are making excellent progress on underground infrastructure related to the shaft. Subsequent to quarter end, our shaft sinking contractor, UMS Group, mobilized to site and conducted the first blast of our precinct, an important milestone for the project. Looking ahead, we remain fully on track to complete remaining surface infrastructure installations, conclude the precinct phase and initiate our main sync by year-end. Planned capital expenditures for the new external shaft under contract or in the final stages of negotiation increased from approximately 35% at year-end to over 70% at the end of March. With additional equipment orders expected to be placed this quarter, total visibility on project capital is approaching 75%. Like the Tucuma project, I'm pleased to share that our projected capital spend on the shaft remains within 5% of budget. I will now turn the call to Wayne to discuss our financial results for the quarter.