Brant E. Hinze
Analyst · Stifel, Nicolaus
Thanks, Paul. I'll be providing a review of our operations and an update on our priority growth projects in a moment. As Paul mentioned, during my regular quarterly meetings in the regions, we rolled out the Kinross Way Forward to our regional vice presidents and site leaders. Those regional teams will be driving the process and as we advance our efforts, it is still very early days in the process but I can tell you about a few wins so far. In the area of capital efficiency, we have identified approximately $200 million in CapEx reductions and eliminations and deferrals. As a result, we have reduced our CapEx forecast for 2012 from $2.2 billion to $2 billion. In supply chain management, we've made several gains. We've moved to a global strategy for cyanide procurement with a long-term contract with our preferred supplier starting in January 2013. The benefits will come from securing a supply at contracted rates, which will mitigate production losses or spot price purchases. We are also moving to a global strategy for explosives and have just launched the global tender for 3 of our sites with the goal of selecting suppliers by the first quarter of next year. With respect to tires, in order to mitigate cost increases due to shortages of Tier 1 tires, we have done 2 things. First, we have just secured sufficient supplies of Tier 1 tires to meet our 2013 requirements. Second, our continuous improvement program for tires has led to achieving as much as 12,000 hours on our large-class, haul-truck tires at some sites, which is far beyond industry average. Again it is still early days and these are just a few initial examples, but they help to illustrate the directional changes we'll be making as we advance the Kinross Way Forward across the organization. Speaking now to our third quarter operating results. Production from our sites in North America was strong this quarter, in line with expectations for higher production from the region in the second half of 2012. Fort Knox's strong performance was due to an increase in tonnes of ore mined and processed, higher mill grades and mill recoveries as well as accelerating heap leach production. The improved recoveries were largely a result of several initiatives the Fort Knox team put in place earlier this year, including water and solution management and carbon strip schedules. Round Mountain's third quarter production was consistent compared to quarter 2 due to strong heap leach performance. Kettle River-Buckhorn had an excellent quarter largely due to increased grades as we were mining a higher grade portion of the orebody. Regional cost of sales per ounce improved compared to the second quarter mainly due to higher production. We expect North America to complete the year at the high end of production guidance and within cost guidance for the region. In South America, regional third quarter results were lower compared with quarter 2, mainly due to lower-than-expected production from Paracatu. The production at Paracatu was impacted by lower recoveries at both Plants 1 and 2. We have established a task force to focus on recovery opportunities, and we expect improvements in quarter 4. We began commissioning the fourth ball mill during the third quarter and it is expected to be completed by year end. At Maricunga, suspended solids in leach solution impacted production for the quarter. This has now been addressed and, as a result, we expect production to improve in the fourth quarter. At La Coipa, stronger silver grades and improved gold recoveries resulted in higher third quarter production when compared to second quarter. Full-year production and cost guidance for the region remain unchanged. In West Africa, third quarter production and cost of sales at Tasiast improved compared with the second quarter. However, production was negatively impacted by variability in gold grade that continues to be encountered in the banded iron formation-type ore currently being mined in the Piment pits. Water supply rates continued to impact leach production. However, ongoing repairs to the existing pipelines are expected to progressively improve water availability through remainder of the year. At Chirano, production for the quarter was slightly higher than quarter 2, 2012, as a result of improved plant throughput. Although operating cost per ounce are higher for the region than we would like, we are maintaining our full-year production and cost guidance for West Africa. In Russia, production at Kupol increased from the second quarter due to slightly higher throughput. The mill achieved record throughput this quarter and continues to exceed throughput expectations, averaging over 3,500 tonnes per day. This increase was achieved largely through continuous improvement initiatives and is a result of excellent work by the team at site. The Kupol team has systematically evaluated every aspect of the circuit to reduce bottlenecks and increase throughput, and their success is a great example of continuous improvement in action. We expect Kupol's strong performance to continue in the fourth quarter and expect full-year production to be at the high end of guidance with costs at the lower end of guidance for the region. Overall, it was a solid quarter from our portfolio of operations with improved production and costs compared to quarter 2 of this year, and we're on track to meet our 2012 productions and cost guidance. Moving from operations over to our projects. We continue to advance the key development priorities, which are Dvoinoye and Tasiast. At Dvoinoye, we made good progress through the third quarter of 2012, and the project continues to be on schedule to deliver first ore to the Kupol mill in the second half of 2013. Underground development is 52% complete and is progressing ahead of plan. We have installed and initiated commissioning of the 2 main mine fans and supporting power equipment. Construction of infrastructure and surface facilities is 45% complete, and construction of the all-season road between Dvoinoye and Kupol has progressed well. All necessary permits for the current scope of underground development and construction activities are in place. At the Tasiast expansion project, we completed the column test program we began earlier this year to determine the viability of sulphide heap leach. We currently leach low-grade, run-of-mine oxide successfully without crushing. Sulphide samples were taken from different representative zones of the orebody, and the overall average grade recovery obtained was approximately 60%. Based on this recovery level, we have concluded that heap leaching is not an economically attractive alternative to CIL processing for sulphide ore. We have also concluded that capital investment in a fine crush, heap leach option to supplement CIL production is not justified at this time. As we mentioned last quarter, we expect to complete a pre-feasibility study for the construction of a mid-sized expandable CIL mill in the range of 30,000 tonnes per day in the first quarter of 2013. The pre-feasibility study has been entirely focused on CIL milling as a preferred processing approach for the project and does not contemplate heap leaching. Therefore the economics of the pre-feasibility study will not be affected by the heap leach test results. We continue to make basic infrastructure improvements at Tasiast, including the permanent camp, truck shop, warehouse facilities, West Branch dump leach pads, main access road upgrades and stripping at West Branch. Permitting for the seawater supply system is progressing on schedule. At FDN, we continue to advance our optimization studies in parallel with the government negotiations. We're exploring alternative processing scenarios for the project, including the potential for gravity float leach. This could result in lower CapEx and reduced operating risk while improving overall project economics. Taking a brief look at exploration, we are encouraged by the results this year, particularly at Tasiast, Chirano, La Coipa and Kupol. Since acquiring Tasiast in 2010, the majority of our focus was on delineating the Greenschist Zone at West Branch. This year we have accelerated our drilling program in the district outside of the main Tasiast orebody. We've completed approximately 2,400 holes or over 200,000 meters of drilling year-to-date up and down the 80-kilometer belt. We have encountered encouraging results at 7 new targets along with positive results in the follow-up drilling at C67 and C68. At Chirano, drilling under the open pits has returned positive results which reinforce the potential for mineralization to continue at depth. At La Coipa our infill drilling program was completed at the Pompeya discovery, along with metallurgical, geotechnical and condemnation work. The project is in the process of transitioning from exploration to our projects team as we continue to advance this opportunity. Recent drilling on the Kupol West license to follow up results in previous holes at our Moroshka target has encountered further encouraging mineralization along strike and at depth. Moroshka is located 4 kilometers east of Kupol, and we are continuing work in the fourth quarter to understand the significance of these results. I'll now turn the call over to Paul Barry.