Rob Atkinson
Analyst · JP Morgan. Please go ahead
Thanks, Tom. Turning to slide 10. The strength of our diversified global portfolio along with our operating model and capable workforce continues to be a key differentiator for Newmont during this unprecedented time. During the second quarter, we executed safe and efficient restart plans at Cerro Negro, , Yanacocha, Éléonore, Peñasquito and Musselwhite, which I will discuss in more detail shortly. As Tom mentioned we continue to maintain the extensive protocols across all of our sites to ensure the health and safety of our workforce in nearby communities. And we have been operating with a significantly reduce site based workforce and remain committed to the safe delivery of our plan. As you will recall, we made the important and proactive decision to continue paying our employees through June, despite the status of their operation, which has impacted our second quarter unit costs. It was absolutely the right decision. And it has been an essential factor to allow the safe and efficient ramp up of our operations with the full support of our workforce and local communities. For the second quarter, we incurred approximately $195 million of care and maintenance costs, and approximately $33 million of COVID-19 specific costs related to additional health and safety procedures, transportation costs, and community support fund disbursements across our entire portfolio. Over the last few months, we've seen near term headwinds as our increased health and safety protocols impact operating efficiencies, particularly in the mine, with staggered pre-start meetings, the elimination of hot [ph] heating and transport changes impacting productivity. However, we've been able to partially offset these impacts by reducing the number of people working at site, implementing new rosters and taking advantage of downtime to plan for longer term efficiency improvements. Now we'll touch on these further in the regional overviews. I'm very proud of our team and what they've safely accomplished during this unprecedented time. But as we continue navigating through this global pandemic, I can assure you, our focus to drive efficiency and productivity gains is more important and acute than ever. And we are well-positioned to deliver stronger second half of the year. Coming now to slide 11, for an update on Australia's performance. At Boddington, we began to reach high-grade in the south pit. An earlier this month, the team achieved 21 million tonnes through the plan year to-date, which puts them on track to exceed 40 million tonnes by year end. As our three-year stripping campaign nears completion. We will continue to mine higher grades into 2021. We continue to invest in the Autonomous Haulage System, which we expect to be fully operational next year. Tanami delivered yet another solid quarter, and the team is continually looking for ways to improve the way we work. Just recently, the mine implemented even time rosters to improve productivity and shift change these. With the interstate border closures in place in Australia, I am incredibly appreciative for many of the team and their families for their willingness to temporarily relocate to Darwin from other parts of Australia, allowing us to continue safely operating through this period. The Tanami Expansion 2 project is also progressing and all critical activities have continued. Working with our EPC Worley [ph] we are now approximately 30% through the engineering design, and the overall project is about 10% complete. Travel restrictions did impact second quarter development rates. However, we recently added a fourth crew to help mitigate the efficiency losses. In early July, the box cut for the production Chase Foundation was completed, and we placed the second raisebore on surface. So overall things are tracking well. And two weeks ago, the first buildings for the new camp near the underground mine arrived on site after traveling over 2000 miles. The camp will initially be used for the construction crews and when the project is completed, it will be repurposed to accommodate our mining crews to improve fatigue management and save 80 minutes a day in travel time between the current camp and the mine. We are also progressing our study work of Oberon remotely including a review of surface layers, mine and process plant infrastructure options and updating the resource model. Our hydro-geological drilling has been delayed, but we are working with the traditional owners to access that area and see if we remobilize the team. The Oberon deposit continues to grow as an open pit opportunity and the potential to get beyond 2 million ounces as we define the high-grade structures and understand the upside of this prospective deposit, and how this further improves our production outlook. Australian's 2020 production and cost outlook is unchanged, with approximately 1.2 million ounces and $900 per ounce AISC. Turning to Africa on Slide 12. Ghana has seen an uptick in COVID cases over the last two months, but our teams at Akyem and Ahafo continue to adhere the strict protocols and on quarantine and contact tracing procedures have been effective and minimizing the impact to our operations. Our team delivered solid second quarter performance with higher throughput despite a plan maintenance shutdown, and expects to reach higher grade in the fourth quarter. At Ahafo, we continue to progress stripping at the Awonsu and Subika open pits, while advancing underground development for the updated mining method at Subika Underground. Development rate of Subika Underground are ahead of schedule, and we recently received the raisebore machine, which will further support development progress. The 2020 outlook for Africa is unchanged with 850,000 ounces at $870 for ounce AISC. As we expect a strong second half of the year with a half or reaching higher grade than the open pits and Subika ramping up times from the underground. Turning to slide 13 for an update on the Ahafo North project. The Ahafo District provides significant upside potential from the underground opportunities at Awonsu, Apensu and Subika as well as from Ahafo Mill [ph]. Located just 30 kilometers north of our existing Ahafo operation, it is the best on mine gold deposit in West Africa, with approximately 3.5 million ounces of open pit reserves, and more than 1 million ounces of indicated and inferred resource. Similar to Tanami in Australia, our ability to expand this prolific region is underpinned by our successful recent investments in Ahafo Mill expansion and Subika Underground, which has created a very strong platform for our future. Our plans include building a standalone mill, and the project is expected to produce approximately 250,000 ounces per year over a 13-year mine life for an investment of approximately $700 million to $800 million. Our project work continues remotely with a team focused on engineering and design work, as well as construction, procurement and community planning. We have also been able to advance the permitting process with the Ghana EPA through both virtual and limited face-to-face sessions. An earlier this month, we submitted our initial environmental impact statement for review. We also received engineering and design approval from the Ghana Highway Authority for the highway diversion and improvement project, which was a key milestone for the project. We remain on track for a full funds decision in 2021. Moving to our North America operations on slide 14. During the second quarter, the North America region resumed operations at the three sites that were previously in care and maintenance. At Peñasquito, we've been began a phase ramp up in mid-May consistent with the Mexican government's regulations. Government representatives visited the site, including the Federal Undersecretary of Mine to review our protocols, and said Peñasquito is a leading example for how all Mexican mines should operate during these times. We began ramping up the mill and mining activities at the beginning of June and were quickly back to pre-COVID at record levels in the plant by mid June. We remain very focused on delivering value from this world-class asset by applying our full potential program to eliminate constrains, reduce costs and increase productivity and ultimately allow us to extend mine life through resource conversion. As previously highlighted, we also recently completed a definitive agreement to resolve all outstanding disputes with the Cedros community, which was a significant milestone, and which now establishes as a clear path forward for both parties to develop a long term partnership to create value, and importantly, improve lives. This agreement was signed with the community elected representatives and will be ratified in the General Assembly that will take place when COVID-19 gathering restrictions are lifted by the government. With Porcupine and CC&V continued without major interruption during the second quarter. And in Porcupine we saw improved recoveries with a greater proportion of ore coming from the Subika underground. At Musselwhite, we resumed work on the conveying system in early June, after working closely with First Nations leaders and the provincial health authorities on the safe restart plan. By early July, our contract of cementation had its full project team on site, and we are on track to complete the conveyor installation by the end of 2020. The Musselwhite materials handling project will begin mobilizing for completion activities in September to align with the conveyor timeline. We restarted the mill for stockpile processing on June the 19th and resumed the underground mine development work at same time. Our full potential work at Musselwhite is progressing well. And our team successfully completed the diagnose phase entirely virtually in Ahafo Mill. From that work, the Underground work stream identified approximately 25 opportunities to improve development productivity, tracking performance and ore body modeling. I'm excited about future Musselwhite and the ability to drive valuable operational improvements in the year ahead. Turning to Éléonore. We restarted the mill in late May after approximately 60 days in care and maintenance. Earlier this year, the mine undertook a review of ground support conditions, and we completed some necessary rehabilitation one before ramping up production activities. We expect to reach more normal levels of production in August, as we manage through ongoing travel and logistical constraints. Construction on the lower mine materials handling system project resumed in early June with the conveyor belt installation and commissioning of the fresh rock breaker. We expect the project to be operational in mid August, streamlining the transportation of --suffers. From the beginning, we flagged that Éléonore was the operation requiring further optimization as Newmont's technical experts critically assess the asset and the opportunities to improve the geotechnical model. We remain positive on the value we can unlock from Éléonore. However, we are taking the proper time to truly integrate the updated geological and geotechnical models to deliver an optimized life of mine plan. As a result, we expect lower production baseline for Éléonore of approximately 250,000 ounces per year. And work is underway with support from our full potential program to ensure the cost base matches this production level. To support this important work, we've made a number of changes to the site leadership team since the beginning of the year, with a new general manager, mining manager, exploration manager, health, safety and security manager who are all now on board. This leadership team is driving fundamental changes to how we operate with a sharp focus on sustainable improvement choosing back to basics principles in order to build a strong foundation in the year ahead. The years ahead, the North America 2020 outlook has been updated to approximately 1.4 million ounces at $1,040 per ounce AISC, with an additional 880,000 gold equivalent ounces from silver, lead, and zinc. This outlook includes the impact the site previously in care and maintenance and the changes at Éléonore. Turning to South America, on slide 15. Merian delivered solid performance in the same quarter, as higher recoveries partially offset lower ton mine as the site managed through wet season impacts. The team also safely completed plan to reach higher grid as we transition to harder rock. The Yanacocha began ramping up in mid-May after being in care and maintenance for approximately 60 days. Mine and mill activities were suspended during the care and maintenance period. But we continued all critical activities such as water treatment, which enabled ongoing production from the leach pads. The mill restarted in mid May and mining activity resumed in late May. And we expect to reach full operations in September. We are placing Quecher Main ore on the new categorical leach pad since later this year. However Yanacocha's outlook has been updated to reflect leach cycle disruptions in 2020 from the timing of ore placement. At Cerro Negro, we took advantage of the approximately 60-day care and maintenance period to perform a significant amount of mill maintenance and modifications to improve throughput. The team is managing through several constraints including government and provincial travel restrictions, in addition to inclement winter weather. So the mine is currently operating at about 50% capacity. Given the site's that's mine constraint, we are running the mill in campaigns in order to ensure cost efficiency until we are back to normal mining reads. Though potential implementation is underway, and the priorities remain focused on back to basics mining practices, which includes improving development rates, ground control, and backfill practices. The 2020 outlook for Cerro Negro has been updated to include COVID related constraints and our ability to achieve improved development rates and access higher grid ore in the fourth quarter. Looking forward, we remain excited about the potential to extend Cerro Negro's mine through our exploration program, and we recently secured a large land package of approximately 550 square kilometers near Cerro Negro. The South America 2020 outlook has been updated to just over 1.1 million ounces at approximately $1100 dollars per ounce AISC, which includes the impact on the COVID related constraints at Cerro Negro. We are also excited about Yanacocha sulphates progressing towards the full funds decision in 2021. So turning to slide 16. Yanacocha has been a cornerstone asset to the Newmont portfolio for decades, and we continue to see promising drilling results. As you can see here, the first phase of the sulphates project is focused on developing the most profitable deposits and is expected to produce approximately 500,000 gold equivalent ounces per annum through 2030 and extend Yanacocha operations into the 2040. As we advance towards a full funds decision next year, we look forward to providing more information on this exciting project in due course. So wrapping up with our 2020 outlook on slide 17. Despite the decision to place five operations in care and maintenance, we expect to produce approximately 6 million ounces of gold at all-in sustaining costs of $1,015 per annum in 2020, with an additional 1 million gold equivalent ounces from core products. Compared to the outlook provided in mid May, production is unchanged. While our costs applicable to sales has been lowered at $760 per ounce and all-in sustaining costs is unchanged at $1,015 per ounce. Our sustaining capital has increased to $900 million as we've been able to ramp up faster than first anticipated at our operations previously in care and maintenance. Our total 2020 capital expenditure is expected to be approximately $1.4 billion as increases to sustaining capital are partly offset by further changes to the development capital schedule for Tanami Expansion 2 which they fair some spend to 2021. For exploration and advanced projects, we've lowered our 2020 investment to approximately $350 million. We are fortunate to have the largest gold reserves in our industry at 95.7 billion ounces, and we completed the majority of our reserve drilling in the first quarter. However, as we continue to focus on keeping our people safe, we currently expect to replace approximately 60% to 70% of our targeted reserves delivered by the drill bit from our manage operations in 2020. We also experienced some processing delays at the start of the pandemic, but are now seeing normal turnover times. We also restarted exploration mapping activities at coffee using 100% Yukon-based crew and we are prepared to restart greenfields like activities as soon as local restrictions are lifted in areas of Africa, Australia and South America. Our longer term target of organically replacing at least two-thirds of reserves depletion over the next 10 years remains firmly intact. The changes to the way we operate from COVID have been substantial. And as the pandemic continues to evolve with the potential for a second wave, its becoming more likely, we may have to take further measures to protect our workforce and our communities. And with that, I'll turn it over to Nancy to discuss our financial results on slide 18.