David Garofalo
Analyst · Scotiabank
Thanks, John. John and I are here with the rest of our senior management team in Flin Flon to celebrate 3 auspicious events. Yesterday we marked first ore production at Lalor with our work force and had a fairly major celebration, moved the crew over to Reed where we celebrated the commencement of full scale construction there as well, and today we’ll be marking first ore, at the 777 North expansion, so it’s been a week of celebration, and I want to take this opportunity to thank our workforce in northern Manitoba, Brad Lantz and his team, for their excellent work and delivering these projects on time and on budget.
In the quarter, Hudbay continued to generate steady cash flow from our reliable operating mines, which continue to perform within expectations. It also puts us on track to meet our production targets for the sixth consecutive year. As a result, our production and operating cost guidance remains unchanged for the full year.
We also marked a number of significant growth milestones, accelerating our goal of becoming a leading mid-tier diversified metals producer with long-life, low-cost operations in investment-grade countries.
Last week, our board approved the development and construction of the $1.5 billion Constancia copper project in Peru. In conjunction with that, we also entered into Precious Metals Stream Transaction with Silver Wheaton for upfront deposit payments of $750 million and are currently arranging a new $600 million credit facility.
At our Lalor project near Snow Lake, Manitoba, we reached a major milestone, as I said, with first ore production just this past Sunday in fact, and the project remains on time and on budget.
Lalor is now poised to reach early production of 1,200 tonnes of ore per day using the vent raise [ph]. Progress at Lalor is truly remarkable when you consider the deposit was discovered only 5 years ago.
Development of our joint venture Reed copper project is also progressing on schedule, significant surface infrastructure is in place or on order and the portal area is approximately 70% complete. First production at Reed remains on track for late 2013.
And finally, our 777 North expansion is also on track and on budget. This expansion will allow us to access the Northern portion of the 777 mine by ramp, giving us a new means of egress and enabling establishment of underground drill platforms. First ore should be drawn from 777 North this fall.
Total revenue for the second quarter of 2012 was $189.9 million, $57 million lower than the same quarter in 2011 as a result of lower realized metal prices and lower concentrate sales volumes. Year-to-date, revenues was $376.9 million, $47.3 million lower than the same period in 2011 as a result of lower prices.
Operating cash flow was $66.1 million in the second quarter of 2012, a $4.3 million increase compared with the same period last year.
Cash flows this quarter included a current tax recovery of $18.2 million to reflect the reduction of prior taxes owing as a result of accelerated depreciation of prior year tax pools related to the new mine status ruling at the Lalor mine.
Year-to-date operating cash flows were $108.4 million, reflecting an increase of $4.7 million from the same period in 2011 for the same reasons.
Our cash and cash equivalents decreased to $710.1 million at the end of the quarter. This decrease was expected and was mainly driven by $175.8 million in year-to-date capital expenditures, primarily relating to our Lalor and Constancia projects.
We expect to fund our 3 mine development projects over the next 3 years through a combination of cash on hand, funds from our stream agreements and credit facilities and cash flow from operations.
Our operating team continued to work safely and efficiently, which led to another productive quarter. We maintained our track record achieving good cost control and exemplary safety performance at our operations, as all of our mines and processing facilities achieved targeted cost per tonne.
Trout Lake, however, exceeded expectations, even as we permanently shut down the mine after 30 years of operation.
At Lalor, development and construction of our fully-owned Lalor project is advancing well. Our cost remained on budget. To date, we’ve invested approximately $277 million on the project and have entered into additional $91 million in commitments for the project out of a total project commitment of $704 million.
During the quarter, the main ventilation shaft sinking was completed, mine air flow ventilation is now available on the 810 and 840 meter level breakthroughs. We removed the vent shaft services for sinking to enable the company to hoist up to 1,500 tonnes of ore and waste per day this month.
The ore will be processed at the nearby Snow Lake concentrator until late 2014, when we expect to begin production from the main shaft and new concentrator in late 2014. The first full year of production from the main production shaft is expected in 2015.
Basic engineering for the new concentrator is 80% complete. We have placed orders for the surface crusher and the SAG and ball mills. Site geotechnical work is complete and the company is finalizing the final site leveling required for the concentrator footprint.
The main production shaft is currently sunk to the 200 meter level and is 20% complete relative to its planned depth of 985 meters. All other surface infrastructure is essentially complete and underground development is well-advanced. The installation of a new copper circuit, the Snow Lake concentrator is currently underway and commissioning is planned for September to facilitate processing of Lalor ore.
Underground development and construction work has been ongoing on the 795-, 810-, 825- and 840-meter levels.
At Constancia, front-end engineering and design work is now complete. The principal beneficiation concession or construction permit was granted in June 2012 and other required permits are expected in the ordinary course.
Site activity to date has included the completion of a 660-bed construction camp, mobilization of the EPCM and civil works contractors, and the ongoing construction of homes for the 14 families that are scheduled to be moved from the project site later this year. The remaining 22 families are planned to be relocated next year.
As noted in last week’s announcement, Constancia’s development schedule contemplates 9 quarters of construction with initial production late 2014 and full production commencing in the second quarter of 2015.
This timeline to completion is shorter than previously forecast and reflects the progress that has been made in the past year at the project in front-end engineering, design, permitting and community relations.
Out of the total project capital cost estimate of USD 1.5 billion, we have fixed price orders and supplier commitments for approximately USD 252 million in project equipment, including grinding mills and mobile equipment. We have spent USD 91 million of total estimated capital costs of project as at June 30, 2012.
On the exploration front, our focus at Constancia will be on expanding Pampacancha and drilling there is underway. Two drills are concentrating on infill drilling, as well as testing the extension of the deposit to the north and the west. The exploration program has been modified to an expected 18,000 meters for 2012, due to the continued requirement for geotechnical drilling to support detailed engineering.
At the Chilloroya South prospect, we expect to begin testing gold and porphyry copper targets this month. This exploration program will also concentrate on previously identified high priority targets within the mining concessions. The Chilloroya community has ratified an exploration agreement with Hudbay that allows us to access these exploration prospects for drilling over the next 3 years.
At our 70% owned Reed copper project, just 120 kilometers east of Flin Flon, Manitoba, our focus is on the preparation of the project site for portal development. The project is on schedule, as we began the trench excavation in June 2012.
We also completed the SAG leveling for the mechanical shop and warehouse office, changehouse and parking lot pads, as well as camp expansions to accommodate the workforce through the development stage of the project.
Materials and equipment from the Trout Lake mine have begun arriving at site, and we’ve ordered new mobile equipment and compressors for delivery in the third quarter of this year. Tenders for the mechanical shop and warehouse have also been issued.
Initial production at the Reed copper project is expected by the fourth quarter of 2013, and ramp-up to full production of approximately 1,300 tonnes per day is anticipated for the first quarter of 2014.
Our transformation to a leading mid-tier diversified producer with long-life, low-cost operations in investment-grade countries is underway, and is being accelerated by the progress we’ve made to date in Constancia. Production in all of our key metals is anticipated to grow considerably in 2015, with 420% growth in copper, 35% growth in zinc and 125% growth in precious metals.
Advancing Constancia, while meeting our corporate objective and maintaining and growing per share metrics is important. The Precious Metals Stream Transaction of the term loan we announced last week are not dilutive to our shareholders and are critical to helping us meet this important objective.
On a final note, after more than 30 years of service, we closed our Trout Lake mine at the end of June. Trout Lake’s enduring legacy is one that makes all of us proud, and I would like to thank all of the men and women that made it one of Hudbay’s most successful mines in our history.
Thanks for your time today, and operator, we are pleased to take questions.